We dont have 2 way radio's here,we use Hutterites.We have a couple young lad's hired on from the colony and they like to run.This is minimal disturbance so you have to walk to where the pipe is geeting laid.
They will run a mile down the right of way with a message full tilt.
then at dinner will order a 12 inch pizza,huge steak with shrimp and 2 cheeseburgers with fries and gravy and eat the whole works.
I dont think Ive seen harder workers in my life.
They broke away from the colony a few years ago to go pipelining.
We stopped mainlining at 3:00 today and got 400 meters.The competition going the other way took 2 days to get that.(boulder construction) Not bad for a 3 meter ditch on a 45 degree slope.
That makes for a huge spill pile.